نوع فایل:power point قابل ویرایش: 30 اسلاید انگلیسی قسمتی از اسلایدها: •The process engineer in a medium-sized machine shop has the choice of machining a particular part on either of two machines. Orders for this part are received regularly, but on a recurring basis. The order size varies. When the order is processed on Machine A, four setup operations of 1 hour each are required. Once set up, the per unit machining time on Machine A is .5 hours. •When the order is processed on Machine B, eight set-up operations of .75 hour each are required. Once set-up, the per unit machining time on Machine B is .55 hours. The hourly wage rates for the machine operators are $10 and $9 for Machine A and B, respectively. The hourly overhead rates (including setup time) are $15 and $13.5 for Machine A and B, respectively. •A) Which machine is preferred if the order size is 100 units? 500 units? •B) What is ...